2 Main Events of 1999 and Early 2000
2.1 As evidence of the North Sea’s productivity, 1999 proved to be another record year for oil and gas production. However, approval of new development activity was limited, largely due to a combination of global factors, most significant of which was the lack of investment confidence surrounding uncertain oil prices.
2.2 Sanctioned development drilling and construction continued throughout 1999 and the trend in oil developments towards small sub-sea tie-backs to existing infrastructure is expected to continue. In the Southern North Sea, satellite gas accumulations are increasingly being developed utilising very small and simple unmanned surface facilities.
2.3 There was further development of the Outer Moray Firth with the approval of the Blake field as a sub-sea satellite to the Ross FPSO. The field is expected to start production in 2001. Cost sharing will help extend the economic life of the Ross field and will lead to a substantial increase in recoverable reserves. Blake has been a good example of co-operation between licence groups leading to the best use of infrastructure to achieve an overall optimum development. Further appraisal of this area is planned for 2000, which is expected to lead to development of the more gas prone part of the basin.
2.4 A notable highlight for 1999 was BP Amoco’s world record extended reach well in Wytch Farm. This established records for both the longest production well (measured depth of 11,278 metres) and also the greatest horizontal distance (10,728 metre step out).
2.5 A total of 137.1 million tonnes of oil was produced in 1999.
2.6 Production commenced at nine offshore oil/condensate fields during 1999: Egret (Jan), Pierce, Janice and Renee (Feb), Ross (Apr), Rubie (May), Gannet G (June), Buckland (Aug) and Orion (Sep). One onshore oil field came onstream: Newton-on-Trent (Jan).
2.7 During 1999, 48.2 million tonnes of UKCS oil (including natural gas liquids) was delivered to UK refineries, representing 35.3% of total deliveries. Throughout the same period, 3.2 million tonnes was delivered to other UK sites such as petrochemical plants and storage depots. Exports of UKCS oil (including NGLs) in 1999 amounted to 85.1 million tonnes, compared to 35.2 million tonnes of imports. Exports were almost entirely to the markets of other member countries of the European Union or of the International Energy Agency. The majority of the remainder went to traditional markets. Table 2.1 shows the sources of UKCS crude oil received at UK terminals.
Table 2.1 - Oil Terminals Receiving UKCS Crude Oil in 1999
| Terminal | Location | Fields Connected | 1999 Receipts | 1999 Exports (1) |
| (million tonnes) | ||||
| Sullom Voe | Shetlands | Brent
System, Brent, Cormorant North, Cormorant South, Deveron, Don, Dunlin, Dunlin SW, Eider, Hudson, Hutton, Hutton NW, Merlin, Murchison, Osprey, Pelican, Tern, Thistle. |
31.5 | 21.8 |
| Ninian System Alwyn North, Columba B, Columba D, Columba E, Dunbar, Ellon, Grant, Heather, Lyell, Magnus, Magnus South, Ninian, Strathspey. |
||||
| Flotta | Orkneys | Chanter, Claymore, Galley, Hamish, Highlander, Iona, Ivanhoe, MacCulloch, Petronella, Piper, Renee, Rob Roy, Rubie, Saltire, Scapa, Tartan. | 9.7 | 7.2 |
| Forties (landward) | Hound Point (via Cruden Bay) |
Andrew, Arbroath, Arkwright, Balmoral, Beinn, Birch, Brae Area, Brimmond, Britannia, Bruce, Buchan, Cyrus, Drake, Egret, Erskine, Everest, Fleming, Forties, Glamis, Heron, Kingfisher, Larch, Lomond, Machar, Marnock, Miller, Monan, Montrose, Mungo, Nelson, Scott, Sedgwick, Stirling, Telford, Thelma, Tiffany, Toni. | 41.1 | 17.1 |
| Teesside | Auk, Clyde, Gannet A, B, C, D, F, G, Janice, Joanne, Judy, Leven, Medwin, Orion. | 7.9 | 5.6 | |
| Nigg Bay | Cromarty Firth | Beatrice(2) | 0.5 | 0.2 |
| Total | 90.7 |
59.7 |
||
Chart 2.1 - 1999 Oil Production by field (million tonnes)

2.8 In 1999, gas produced from the UKCS increased to 105.0 billion cubic metres (3.71 trillion cubic feet). This includes gas used by operators for drilling, production and pumping operations. Production commenced at nine new offshore gas fields: Corvette (Jan), Bell, Dalton and Millom (Aug), Ketch, Sinope and Vampire (Sept), Neptune and Mercury (Dec), and at one new onshore gas field: Saltfleetby (Dec). Gas production data can be found at Appendix 10 (note: Neptune and Mercury are not included there as data for these fields was not available at the time of print). Additional supplies of gas associated with crude oil extraction also started coming ashore in 1999 from nine new oil fields. These additional fields have contributed to increased production of gas from the main pipeline systems seen during 1999.
2.9 After taking into account the 7.8 billion cubic metres of gas landed in the Netherlands from the UK share of the Markham transboundary field and from the Windermere field, of gas exported to the Irish Republic from Scotland, and gas exported to Belgium via the Interconnector from Bacton, total sales of UKCS gas to UK gas suppliers amounted to 90.9 billion cubic metres (3.21 trillion cubic feet) in 1999. (5.2 per cent higher than in 1998). In addition 1.1 billion cubic metres (0.04 trillion cubic feet) of gas were imported from the Norwegian Lille Frigg, East Frigg and Frøy fields and from the Bacton-Zeebrugge Interconnector. Imports made up 1.3 per cent of total gas supplies in the UK in 1999, compared to 1.0 per cent in 1998.
2.10 Details of the top ten gas producing fields in 1999 can be seen at Table 2.2. Chart 2.2 shows levels of gas production.
Chart 2.2 - 1999 Gas Production (billion cubic metres)

2.11 Table 2.3 shows detail of the sources of UKCS natural gas received at UK gas terminals. Terminals operating at Bacton accounted for 19 per cent of gas supplied into the UK in 1999.
Table 2.2 - Top Ten UKCS Gas Producing Fields in 1999
| Field/Area | Terminal linked to: | Net
production in 1999 (million cubic metres) |
As per cent of total UK production |
| Morecambe South | Barrow-in-Furness | 9,823 | 10.0 |
| Britannia | St. Fergus (via SAGE) | 6,862 | 7.0 |
| Brent | St. Fergus (via FLAGS) | 6,145 | 6.2 |
| Bruce | St. Fergus (via Frigg line) | 5,043 | 5.1 |
| Brae Area | St Fergus (via SAGE) | 4,661 | 4.7 |
| Armada | Teesside (via CATS) | 4,237 | 4.3 |
| Beryl Area | St Fergus (via SAGE) | 3,088 | 3.1 |
| Leman | Bacton | 2,850 | 2.9 |
| ETAP | Teesside (via CATS) | 2,610 | 2.6 |
| Viking | Theddlethorpe | 2,435 | 2.5 |
| Top 10 fields | 47,754 | 48.4 | |
| UK Total | 98,708 |
Table 2.3 - Gas terminal receiving UKCS Natural Gas in 1999
| Terminal | Fields Connected | 1999
Receipts (billion cubic metres) |
| Bacton | Baird, Barque, Barque South, Bessemer, Bure, Bure West, Camelot C and S, Camelot N, Camelot NE, Clipper, Corvette, Davy, Dawn, Deben, Delilah, Excalibur, Galahad, Galleon, Gawain, Guinevere, Hewett, Indefatigable, Indefatigable SW, Lancelot, Leman, Malory, Mordred, Orwell, Sean, Sean East, Thames, Trent, Tristan, Tyne North, Tyne South, Welland NW, Welland S, Wensum, Yare. | 19.3 |
| Barrow-in-Furness | Dalton, Millom, Morecambe North, Morecambe South. | 11.0 |
| Dimlington | Cleeton, Johnston, Ravenspurn North, Ravenspurn South. | 2.8 |
| Easington | Amethyst East, Amethyst West, Hyde, Newsham, West Sole. | 2.5 |
| Point Of Ayr | Hamilton, Hamilton North. | 1.9 |
| Far-north Liquids and Associated Gas System (FLAGS) (St Fergus) | Brent, Cormorant North, Cormorant South, Magnus, Magnus South, Murchison (UK), Pelican, Statfjord (UK), Strathspey, Thistle. | 7.6 |
| Frigg Line (St Fergus) | Alwyn North, Bruce, Chanter, Claymore, Dunbar, Ellon, Frigg (UK), Galley, Grant, Hamish, Highlander, Iona, Ivanhoe, MacCulloch, Petronella, Piper, Renee, Rob Roy, Ross, Rubie, Saltire, Scapa, Tartan. | 9.3 |
| Fulmar Line (St Fergus) | Clyde, Curlew, Fulmar, Gannet A, B, C, D, E, F and G, Guillemot A, Kittiwake, Leven, Mallard, Medwin, Nelson, Orion, Teal, Teal South. | 2.1 |
| Miller (St Fergus) | Miller. | 1.0 |
| Scottish Area Gas Evacuation (SAGE) (St Fergus) | Beinn, Beryl, Brae C, E, N, S and W, Britannia, Ness, Nevis, Scott, Sedgwick, Telford, Thelma, Tiffany, Toni. | 14.9 |
| Central Area Transmission System (CATS)Teesside | Andrew, Armada Complex (Drake, Fleming and Hawkins), Egret, Erskine, Eastern Trough Area Project (Heron, Machar, Marnock, Monan and Mungo), Everest, Janice, Joanne, Judy, Lomond. | 13.6 |
| Theddlethorpe | Alison, Anglia, Ann, Audrey, Boulton, Caister B, Caister C, Callisto, Ganymede, Ketch, Murdoch, Pickerill, Schooner, Valiant North, Valiant South, Vampire, Vanguard, Victor, Viking, Vulcan, Waveney. | 11.9 |
| Total (1) | 97.7 |
(1) Excludes 0.8 billion cubic metres exported from the Markham and Windermere fields and 0.3 billion cubic metres produced at onshore fields.
PRODUCTION AND DISPOSAL OF NATURAL GAS LIQUIDS
2.12 NGLs continued to be brought ashore with crude oil supplies via major terminals and also through the Far-north Liquids and Associated Gas System (FLAGS), Fulmar, Frigg and Scottish Area Gas Evacuation (SAGE) pipeline systems to St Fergus. Small amounts of NGLs are also brought ashore via the Central Area Transmission System (CATS) terminal, and through the Norpipe system, to Teesside.
2.13 Production of NGLs in 1999 was 8.8 million tonnes, including 2.0 million tonnes of condensates. The largest quantities of NGLs were piped to Mossmorran and Kerse of Kinneil for fractionation.
2.14 During 1999 14 submarine pipeline works authorisations for the construction and use of 91 additional submarine pipelines were issued. As in previous years, the majority of these were infield flowlines associated with field development. Pipelines brought into use for the first time during 1999 included the Shearwater to Bacton trunk line and 25 interfield pipelines. Details of operating oil and gas pipelines are in Appendix 13.
2.15 The current trend is for the utilisation of existing infrastructure and further development of established fields. Many pipelines authorised in 1999 constitute tying back new wells and sub-sea manifolds to existing facilities, some of which are located in deep water. There is continued interest in Floating Production Storage and Offtake vessels (FPSOs) which are capable of carrying out short term well tests and enable crude oil to be saved rather than flared.
OFFSHORE EXPLORATION AND APPRAISAL
2.16 Five significant discoveries were announced in 1999 (listed in Appendix 5), representing a 30% success rate.
2.17 Overall, though, a number of factors, particularly uncertainty remaining after the fall in world oil prices, led to disappointing levels of exploration drilling. Only 16 exploration wells were started, compared with 47 in 1998. This is the lowest since 1965, which was the second year of drilling on the UKCS.
The number of new appraisal wells (20, compared with 33 in 1998) is the lowest figure since 1971. There were regional variations, though: the Moray Firth held up well and a well was drilled West of Shetland in a record water depth for NW Europe.
Northern North Sea (including East Shetland Platform)
2.18 During 1999, drilling in the Northern North Sea fell to a single exploration well and four appraisal wells. This is a considerable drop on 1998 when 10 exploration wells and 17 appraisal wells were drilled. But the exploration well encountered hydrocarbons, which is encouraging.
2.19 Exploration drilling was at a low level with only two new wells. Interestingly, one well was located in a record water depth of 1,621 metres.
2.20 The Moray Firth showed an increase in activity on the previous year. The five new exploration wells equalled the previous year’s total. Three of them fulfilled 14th and 18th Round drilling commitments. One was drilled on a Fallow Block. The number of appraisal wells jumped from two in 1998 to six in 1999. Most of them focused on the Lower Cretaceous sandstone fairway.
2.21 Three significant discoveries were announced: one on a 1st Round licence and two which started drilling in 1998 under 11th and 12th Round drilling commitments.
2.22 Five wells (including one sidetrack) were started in 1999, compared with twelve in the previous year. All but one of the wells fulfilled outstanding commitments. Appraisal drilling fell from twelve wells started in 1998 to five in 1999.
Chart 2.3 - Sedimentary Basins

2.23 The Vixen field, already approved for development, is the result of one of the three exploration wells that were started during 1999, all in the southern part of the Southern Basin where the Permian-age Rotliegendes sandstone is the main target. One of the wells was a 17th Round obligation.
2.24 Five appraisal wells were started, with some activity in the Carboniferous area. Two sidetracks made for geological reasons are included in the total figures.
2.25 One well was drilled from an onshore drilling site to an offshore target - the first Channel exploration well since 1996.
ONSHORE EXPLORATION AND APPRAISAL
2.26 The number of onshore exploration wells was up, with six drilled in 1999, from five the previous year. Two of them made discoveries, one oil and one oil and gas. One of the 1999 wells was drilled to an offshore target in the English Channel (as mentioned above). Appraisal drilling was down, with only two wells started in 1999, compared with nine in 1998.
2.27 Drilling of offshore development wells was not far below the rate in previous years. A total of 225 wells (including 90 sidetracks) were drilled, compared with 281 in 1998 and 257 in 1997. This brings the total number of Development wells drilled on the UKCS to over 4000 since developments started in 1966. There is a regional breakdown at Appendix 4.
2.28 Eleven development wells were drilled, five of which were side-tracks.
2.29 No seaward licensing rounds occurred during the period covered by this report.
2.30 A licence award over Block 98/11 was made ‘out of round’ in November 1999 to a consortium of companies led by BP Amoco (to test a possible extension to the Wytch Farm field).
2.31 The 9th Round of Landward Petroleum Licensing was announced in January 2000 in the Official Journal of the European Communities. The Round includes all unlicensed acreage in Great Britain above the Mean High Water Mark. The closing date for applications was 5 May 2000 and it is hoped that licence awards will be made soon.
2.32 Under the Petroleum (Production) Act (Northern Ireland) 1964, landward petroleum licensing in Northern Ireland is the responsibility of the Department of Enterprise, Trade and Investment (Minerals and Petroleum Unit, Netherleigh, Massey Avenue, BELFAST BT4 2JP).
2.33 At the end of 1999 there were 9 landward petroleum licences covering an area of some 3150 sq km. The Department operates an open licensing policy and is prepared to consider applications at any time.
FIELD APPROVALS/DEVELOPMENT PLANS
2.34 Under the terms of petroleum production licences, development work and the production of petroleum may be carried out only with the consent of the Secretary of State for Trade and Industry, or under a development and production programme approved by the Secretary of State.
2.35 In 1999 a total of 23 plans were authorised: 14 oil/condensate and 9 gas. These are listed in Appendix 3.
HYDROCARBONS ADDITIONAL RECOVERY PROGRAMME (HARP)
2.36 The DTI’s expenditure in 1999/2000 on the Hydrocarbons Additional Recovery Programme (HARP) was £2.2 million. This programme aims to provide the DTI with the technical support which it requires to fulfil its regulatory function of ensuring maximum recovery of economic oil and gas from UK fields, with due regard to the environment, and to foster and sponsor innovative recovery techniques.
2.37 Dissemination events, including an improved oil recovery research dissemination seminar, a number of workshops and publishing of generic studies undertaken by AEA Technology and the Universities, were carried out during 1999/2000. Further studies and research on improved oil recovery topics were carried out through Joint Industry Projects. The new Joint Industry Projects this year included data mining to justify and enable the management of reservoir-scale geochemical controls on fluid flow and recovery in the North Sea, uncertainty estimation for reservoir flow incorporating strain distribution and geomechanical changes constrained to production data, simulation of multiphase flow in porous media from pore scale to the reservoir scale and gas and hydrates and deep water drilling.
2.38 UKCS reserves may be classified under two main categories - ‘discovered’ and ‘undiscovered’ - together with an intermediate category, ‘potential additional reserves’, which comprises discoveries about which little is known or which fail to meet the technical and economic criteria for entry into the main ‘discovered’ reserves tables. For each of these categories there is a different level of confidence. The greatest certainty is assigned to the discovered reserves which are calculated on a field by field basis from both well and seismic data. Each field is assigned reserves in one or more of the "proven", "probable" and "possible" categories according to their chance of being both technically and economically producible. Less certainty can be assigned to the Potential Additional Reserves (PARs) which are primarily single well discoveries. The least certain are the estimates of undiscovered reserves which are made by a statistical assessment of the likely number and size of mapped but undrilled prospects.
2.39 In this section, except where indicated otherwise, "reserves" means initially recoverable reserves in oil or gas fields, also known as ultimately recoverable reserves. Continuing previous practice, no proven reserves are assigned to fields without approved development plans. In January each year the estimates of discovered reserves of oil and gas for every field, including those discoveries not yet fully appraised and approved for development, are reviewed with the respective operating company to establish the current reserves levels in the categories listed. Each of the discoveries assigned as PARs is also reviewed with the current operating company every year with regard to current status. The estimates of undiscovered reserves are reviewed by area with regard to the additional information that has accrued.
DISCOVERED RECOVERABLE OIL RESERVES
2.40 Table 2.4 gives the estimates of initially recoverable oil reserves in discoveries to date together with the figures from last year for comparison. Oil reserves include both oil and the liquids and liquefied products obtained from gas fields, gas-condensate fields and from the associated gas in oil fields. The overall totals are simply the sum of the individual field figures. Specifications for liquid condensates from gas condensate fields and natural gas liquids (NGLs) vary across the industry but approximate proportions of these hydrocarbon liquids in the total initially recoverable reserves are now 7% as gas condensate liquids and 4% as natural gas liquids. Oil reserves in all approved fields under first time development at 31 December 1999 are shown below Table 2.4 and are slightly lower than last year. The total initially recoverable proven reserves have increased by 115 million tonnes. However when cumulative production to the end of 1999 of 2,444 million tonnes is subtracted, remaining proven reserves stand at 665 million (20 million tonnes less than at the end of 1998).
Table 2.4 - Estimates of discovered recoverable reserves of oil on the UKCS (1) as at 31 December 1999 (figures in brackets are for end 1998)
| Oil Reserves (Million tonnes (2) ) | Proven* | Probable* | Proven plus probable |
Possible* | Maximum** | |||||
| Initially Recoverable Reserves (3) | ||||||||||
| Fields in Production or under development (4) | 3110 | (2995) | 300 | (440) | 3410 | (3435) | 350 | (320) | 3760 | (3750) |
| Other significant discoveries not fully appraised | 0 | (0) | 155 | (135) | 155 | (135) | 190 | (215) | 345 | (355) |
| Total Initially Recoverable Oil Reserves (4) | 3110 | (2995) | 455 | (575) | 3565 | (3570) | 545 | (535) | 4105 | (4105) |
| Cumulative Production to end 1999 (4) | 2444 | (2306) | ||||||||
| Total Remaining Oil Reserves | 665 | (685) | 455 | (575) | 1120 | (1265) | 545 | (535) | 1665 | (1800) |
2.41 Initially recoverable reserves at the proven plus probable level are slightly lower this year at 3,565 million tonnes. New fields have been included, and reserves have also grown in a number of established producing fields and fields under development, but there have been downward revisions due to geological, reservoir engineering and economic re-assessments. After deducting cumulative production, remaining proven plus probable oil reserves stand at 1,120 million tonnes compared with 1,265 million tonnes last year.
2.42 Possible reserves have increased slightly due to limited exploration in 1999 and by shift in status of certain fields previously held as only having potential additional reserves (PARs). When combined with the proven and probable reserves, the resulting maximum possible remaining discovered reserves stand at 1,665 million tonnes, down from 1,800 million tonnes in 1999.
2.43 The 30 million tonne increase in reserves initially present in fields that have now ceased production is due to the cessation of production from the Maureen field and its satellites during 1999.
Chart 2.4 - Discovered Recoverable Reserves - Oil

DISCOVERED RECOVERABLE GAS RESERVES
2.44 Table 2.5 gives the quantities of gas expected to be available for sale from dry gas fields, gas condensate fields and oil fields with associated gas. Equivalent figures from last year are provided for comparison. Gas which has been or is expected to be flared or used offshore is not included.
Table 2.5 - Estimates of discovered recoverable reserves of gas (1) on the UKCS (2) at 31 December 1999 (figures in brackets are for end 1998)
| Gas Reserves (Billion cubic metres (5) ) | Proven* | Probable* | Proven plus probable | Possible* | Maximum* | |||||
| Initially Recoverable Reserves Gas from Dry Gas fields | ||||||||||
| Fields in production or under development | ||||||||||
| Southern Basin | 1225 | (1170) | 80 | (129) | 1305 | (1300) | 85 | (85) | 1390 | (1385 |
| Other areas | 255 | (255) | 25 | (35) | 280 | (290) | 15 | (30) | 295 | (320) |
| Sub Total | 1480 | (1425) | 105 | (165) | 1585 | (1590) | 105 | (110) | 1690 | (1705) |
| Other significant finds not yet fully appraised. | ||||||||||
| Southern Basin | 0 | (0) | 80 | (70) | 80 | (70) | 45 | (50) | 125 | (120) |
| Other areas | 0 | (0) | 25 | (25) | 25 | (25) | 35 | (30) | 60 | (55) |
| Sub Total | 0 | (0) | 105 | (95) | 105 | (95) | 80 | (80) | 185 | (175) |
| Total Dry Gas | 1480 | (1425) | 205 | (260) | 1690 | (1685) | 185 | (195) | 1875 | (1880) |
| Gas from Condensate Fields | ||||||||||
| Fields in production or under development | 360 | (305) | 135 | (145) | 495 | (450) | 100 | (70) | 595 | (525) |
| Other significant finds not yet fully appraised | 0 | (0) | 100 | (65) | 100 | (65) | 115 | (95) | 215 | (160) |
| Total Condensate Field Gas | 360 | (305) | 235 | (210) | 595 | (515) | 215 | (170) | 810 | (685) |
| Associated Gas from Oil Fields | ||||||||||
| Fields in Production or under development | 330 | (330) | 50 | (80) | 380 | (410) | 65 | (40) | 445 | (450) |
| Other significant finds not yet fully appraised | 0 | (0) | 10 | (35) | 10 | (35) | 25 | (55) | 35 | (90) |
| Total Associated Gas | 330 | (330) | 60 | (115) | 390 | (450) | 90 | (95) | 480 | (540) |
| Totally Initially Recoverable Gas Reserves(3)(4) | 2170 | (2065) | 500 | (585) | 2670 | (2650) | 490 | (455) | 3165 | (3105) |
| Cumulative gas production to end 1999 | ||||||||||
| Dry Gas | 1108 | (1058) | ||||||||
| Associated Gas from Condensate and Oilfields | 302 | (254) | ||||||||
| Total Cumulative Production (4) | 1410 | (1311) | ||||||||
| Total Remaining Gas Reserves | 760 | (755) | 500 | (585) | 1265 | (1340) | 490 | (455) | 1755 | (1795) |
Chart 2.5 - Discovered Recoverable Reserves - Gas

2.45 Gas condensate fields now contribute 22 % of the total initially recoverable gas reserves (up from 19% in 1999) and associated gas from oilfields contributes 15 % (17% in 1999). The gas reserves in fields under first development at the end of 1999 are now shown below Table 2.5.
2.46 Initially recoverable proven gas reserves increased by 105 billion cubic metres (bcm) to 2,170 bcm. After deducting cumulative production of 1,410 bcm, remaining proven reserves stand at 760 bcm which is almost the same as last year. At the proven plus probable level the initially recoverable reserves have increased by 20 bcm but the remaining recoverable gas reserves have decreased by 75 bcm. The maximum possible remaining (discovered) reserves of gas now stand at 1,755 bcm.
2.47 The initially recoverable proven reserves of Southern Basin dry gas fields in production or under development have increased over the year by shift from former probable reserves as volumes are confirmed. Otherwise there is little change in dry gas reserves in the Southern Basin from last year. Dry gas reserves in production or under development in areas outside the Southern Basin have decreased slightly at the probable and possible levels. For both categories the dry gas reserves in fields under appraisal have changed only slightly.
Gas from Gas Condensate Fields
2.48 The initially recoverable condensate gas reserves have increased in nearly all probability categories as a result of reviews of fields in production, delineation of fields under development and discoveries during 1999. Some of the increase also comes from stricter definition of gas types, in particular in categorising gas in deeper gas condensate reservoirs below conventional oil reservoirs as condensate gas rather than associated gas.
2.49 Reviews of a number of oilfields already in production have resulted in a decrease in the estimates of their probable associated gas reserves. The stricter application of gas type definitions mentioned in the previous paragraph has also reduced associated gas totals.
POTENTIAL ADDITIONAL RESERVES (PARS)
2.50 Potential Additional Reserves exist in discoveries which do not meet the criteria for inclusion as possible reserves, as defined in Table 2.4. The current estimates as at end 1999 are shown in Table 2.6.
Table 2.6 - Potential Additional Reserves (1)(2)
| Oil: | 85-370 (95-335) million tonnes |
| Gas: | 75-245 (65-235) billion cubic metres |
- (1) Totals have been rounded to the nearest 5 million tonnes of oil or 5 bcm of gas
- (2) Figures in brackets are for end 1998
2.51 The ranges of reserves in this category may vary from year to year. As additional data become available, some reserves may be transferred from this category to the Discovered Recoverable category. Similarly reserves may be transferred to this category from the Discovered Recoverable category.
2.52 The figures shown in Table 2.6 take account of all discoveries made up to the end of 1999 which do not justify inclusion in the Discovered Recoverable category.
2.53 The upsides for the oil and gas reserves ranges are up from last year by 35 million tonnes and 10 bcm respectively. This is due to an increase in the potential reserves for some fields. Also, some fields are no longer under consideration for possible development. Therefore these reserves were transferred from the Discovered Recoverable category. Most reserves discovered in 1999 were allocated directly to the Discovered Recoverable category.
UNDISCOVERED RECOVERABLE RESERVES
2.54 The methodology for calculating this category of reserves remains unchanged from previous years. In areas where detailed mapping has been carried out, prospects are analysed by standard statistical techniques to obtain estimates of reserves within each basin.
2.55 Additional reserves are likely in these areas as no account can be taken of potential new plays and potential traps that may exist beyond the resolution of current seismic penetration.
2.56 The data-base has been modified to take account of new drilling and mapping. Due to the low level of exploration and appraisal drilling in 1999, only two areas have a change in reported range of reserves. New mapping projects in the Southern North Sea have resulted in a slight increase in the upper end of the gas range in that area. The West of Shetland area now includes the acreage designated during 1999 (former ‘White Zone’). The ranges for both oil and gas in the West of Shetland area are reduced due to a revision of the success rates there.
2.57 The Undiscovered Recoverable Oil Reserves are now estimated to lie in the range 250 - 2,600 million tonnes compared with last year’s range of 275 - 2,550 million tonnes. Recoverable Gas Reserves are now estimated to lie in the range 355 - 1,465 bcm compared with last year’s range of 440 - 1,595 bcm.
2.58 The limits of these ranges should not be regarded as minima or maxima. Estimates of undiscovered reserves must be treated with caution. They provide only a broad indication of the ultimate remaining potential. No estimate is made of unconventional gas resources.
2.59 A study by the Economic Advisory Group of the Oil and Gas Industry Task Force’s Vision Workgroup (described in Chapter 1), published as a supplementary paper to the Task Force’s September 1999 Report A Template for Change, provided an alternative, P50 estimate of UKCS yet-to-find reserves potential based on "play" analysis. The study noted that the majority of the yet-to-find potential of some 1,750 million tonnes of oil equivalent which it identified was expected to be in fields of less than 15 million tonnes of oil equivalent. Over two thirds of the potential reserves were expected to lie within 50 kilometres of existing infrastructure. The study identified the frontier basins of the Atlantic Margin as offering the greatest potential for major new reserves.
Table 2.7 - Estimates of Undiscovered Recoverable Reserves on the UKCS (1) . Reserves in Future Discoveries by Geological Area
| Area | Oil (million tonnes) | Range
of estimated reserves (2)(5) Gas (bcm) (3) |
|
| (a)* | Northern and
Central North Sea (56°N-62°N) (4) |
210 - 1,170 | 20 - 195 |
| (b)* | West of Shetland (6) | 35 - 730 | 85 - 655 |
| (c) | West of Scotland | 0 - 520 (7) | Not assessed |
| (d)* | Southern North Sea, Irish Sea and Celtic Sea Basin | 0 - 20 (8) | 250 - 610 |
| (e)* | East Midlands, Weald, Wessex, South East England, North Yorkshire and Lincolnshire | 5 - 30 | 0 - 5 (8) |
| (f) | Other areas of the UKCS (including other land) | 0 - 130 (8) | Not assessed |
| Totals | 250 - 2,600 | 355 - 1,465 |
ESTIMATED POTENTIAL OF THE UKCS
2.60 With cumulative production to date of 2,444 million tonnes of oil and 1,410 bcm of gas, the total remaining reserves are estimated to lie in the range of some 1,000 - 4,630 million tonnes of oil and 1,190 - 3,465 bcm of gas. The reader should understand that the approaches for assessing probabilities are necessarily different for each of the three categories of reserves listed in Table 2.8. Adding the ends of the ranges together, as done here, only indicates the broad scope for the initial reserves. In particular the upper limits of the ranges for the remaining reserves of oil and gas are only indicative of the remaining potential.
Table 2.8 - UKCS Initially Recoverable Reserves
| Oil (million tonnes) | ||
| 3110 - 4105 | (discovered) | |
| 85 - 370 | (potential additional reserves) | |
| 250 - 2600 | (undiscovered) | |
| Total | 3445 - 7075 | |
| Gas (billion cubic metres) | ||
| 2170 - 3165 | (discovered) | |
| 75 - 245 | (potential additional reserves) | |
| 355 - 1465 | (undiscovered) | |
| Total | 2600 - 4875 |
2.61 Since 1976, the DTI has conducted a quarterly inquiry covering all oil and gas exploration and production licensees and also contractors and agents providing services which are unique to the industry. Contractors include companies employed in drilling or operating platforms for the licensed operators, but not companies whose principal work is classified to other industrial sectors such as seismic work or construction. In this inquiry, licensees provide figures on sales and development, exploration, and operating expenditures. Where possible, the development and operating expenditure figures are split between oil and dry gas fields. Figures for the period 1989 to 1999 are presented in Appendix 7, together with the criteria used for splitting oil and gas costs.
2.62 Sales are, of course, affected both by production and prices. Gas production reached a new record annual level in 1999. Oil production has risen each year since 1992, apart from 1997, and reached a record annual level in 1999. Trends in both oil and gas production are illustrated in Chart 2.6.
Chart 2.6 - Trends in the production of oil and gas, 1970 to 1999

2.63 The annual average price received for gas by UKCS producers rose in most years until 1991, before dropping back a little for the next two years. Between 1994 and 1998, prices remained fairly static at 16 to 17 pence a therm, but fell considerably in 1999. The average price received in 1999 was some 13 p/therm compared with just over 16 p/therm in 1998. Annual prices for sales of oil and gas from the UKCS are shown in Chart 2.7
Chart 2.7 - Average oil and gas prices from UKCS sales, 1976 to 1999

2.64 The annual average price received for oil rose rapidly between 1978 and 1984 but then fell sharply. Prices rose in the latter half of 1990 due to the Gulf crisis, but were then affected by the weak world economy and uncertainty on the restoration of Iraqi production. Oil prices hit a fifty-year low in real terms in December 1998, so that at the beginning of 1999, low prices were causing great concern to the industry with only just over £50/tonne received in the first quarter. However, during the year oil prices improved so that near £108/tonne was received in the last quarter. The average oil price received by producers from sales of UKCS oil in 1999 was some £80/tonne, around a third higher than received in 1998.
2.65 The total income of the sector rose to over £19 billion in 1999, after declining for two years. The rise was largely due to sales of oil, the largest component of the sector’s sales, which rose to £10.3 billion. Proceeds from the sale of gas fell slightly to near £5.1 billion. Other income of operators and production licensees, which had risen since 1990, fell back to just over £1.4 billion in 1999. The income due to contractors and exploration licensees decreased to £1.8 billion.
2.66 Operating costs for oil and gas extraction are estimated to have remained close to £4.2 billion in 1999, despite the rise in production to a record annual level. Thus operating costs per tonne fell again after the rise in 1997 had spoiled the reductions seen since 1991. This is shown in Chart 2.8, which gives operating costs per tonne in real terms. The fairly continuous rise from 1976 to 1991 is not unexpected as unit costs of fields rise when production begins to fall. Also, new fields often pay to use existing infrastructure so that operating costs are high but capital costs are reduced.
Chart 2.8 - Unit operating costs in 1999 prices, 1976 to 1999

2.67 Expenditure on exploration and appraisal (E&A) is estimated at £0.5 billion in 1999, having fallen from £.0.75 billion in 1998 and £1.2 billion in 1997. The number of well starts fell markedly from 80 to 36 (from 59 to 31 excluding sidetracks).
2.68 Production investment (i.e. other than on E&A) in the mineral oil and natural gas extraction sector was buoyed by increasing oil prices from 1979 until their fall at the end of 1985, when it declined in real terms until 1987. Investment reached near to £5 billion between 1991 and 1993 with the development of an unusually high number of large projects and fell, not surprisingly after these high levels, to some £3.75 billion in 1994, before recovering again to some £4.4 billion in 1995, 1996 and 1997.
2.69 Production investment reached £5.1 billion in 1998, but fell back in 1999 to some £3.2 billion.
2.70 Investment on construction and installation of platforms and associated equipment, and on related pipelines and terminals, is estimated to have fallen by around 40% to some £2 billion for the development of oil fields from £3.2 billion, and to £1.15 billion for the development of gas fields from the £1.9 billion seen in 1998. The share of expenditure rose on platform structures and equipment for gas fields, and on development wells rose again for both oil and gas fields.
2.71 Production investment on the UKCS each year since 1976, together with the division between oil fields and gas fields, is shown in real terms in Chart 2.9.
Chart 2.9 - UKCS production investment, 1976 to 1999

2.72 The total project investment committed by operators to projects approved in 1999 was £0.2 billion at 1999 prices. This figure excludes the capital cost of hired equipment. The corresponding figure for investment in 1998 was £1.3 billion at 1998 prices. Total investment since 1965 to the end of 1999 is estimated to have been some £105 billion, including £23.5 billion on E&A. Revalued to 1999 prices, this represents an investment of some £187 billion, including £41 billion on E&A.
2.73 To take account of both capital and operating costs, estimates have been made of the field life cost per barrel for all oil and condensate fields which have been approved, taking into account associated gas produced with oil - see Table 2.9. These overall estimates, which are rounded to the nearest £0.5/barrel, are based on the estimated production and costs of the fields together with their equity share of pipelines and terminals, before the payment of royalty and taxes. They include the costs of development and operation over the expected life of the fields, but exclude abortive exploration costs not attributable to individual fields. A real return on capital of 10 per cent is assumed. The figures can therefore be interpreted as the constant real oil price which would yield a pre-tax real rate of return of 10 per cent.
Table 2.9 - Unit costs of fields at 1999 prices
| Oil
fields* £/barrel |
Gas
fields p/therm |
|
| Fields starting production before 1980 | 11 | 9 |
| Field starting production 1980-85 | 16 | 23 |
| Fields starting production 1986-90 | 14 | 21 |
| Fields starting production 1991-99 | 9 | 14 |
| All fields in production | 11 | 13.5 |
2.74 The industry responded to the fall in oil prices at the end of 1985, and brought the cost of oil fields down so that those starting production in the period 1986 to 1990 require an average of £14 a barrel to obtain a return of 10 per cent. Costs for fields starting since 1991 have been reduced substantially so that they need an average of only £9 a barrel over their production lives. For all oil and condensate fields now in production, an average of £11 a barrel is required.
2.75 The equivalent calculations for gas fields also show a large rise in costs for fields starting between 1980 and 1985, the success of efforts to reduce costs since then, and the need for continued cost reduction. The equivalent average price required for all gas fields in production is 13.5p/therm.
2.76 The direct impact of oil and gas production has improved the UK balance of payments considerably. In 1980 oil made a net contribution of £0.3 billion. By 1985, this had risen to £8.0 billion. The contribution of oil has not reached that level since due to the fall in prices, but has always remained positive. It is estimated at some £4.0 billion in 1999.
2.77 Since the start of major development in 1965, the industry has generated operating surpluses totalling some £250 billion of which over £105 billion, including £23.5 billion E&A, has been re-invested in the UK oil industry.
2.78 The oil and gas industry’s share of total Gross Value Added (which is now used by National Accounts to measure the contribution of industries, rather than Gross Domestic Product) rose between 1992 and 1996 with increased production but fell to 1.7% by 1998 and rose to 1.8% in 1999 following the recent rise in oil prices. Capital investment, including E&A, formed around 13 per cent of total UK industrial investment, and nearly 2.5 per cent of gross fixed capital investment
2.79 The Government’s objective is to maximise the benefits to the nation from the exploitation of its hydrocarbon resources. Government revenues from oil and gas produced on the UK Continental Shelf are made up of Royalty, Petroleum Revenue Tax (PRT) and Corporation Tax. The fiscal regime is designed to extract economic rent and secure a fair share of profits for the nation, while offering stable, attractive and economically sound investment conditions to the oil industry. It is described more fully in Chapter 3.
2.80 Receipts to the Government from taxes and royalties on oil and gas production (including licence fees) reached a peak of £12.2 billion in 1984/85 (equivalent to £22.7 billion in 1999/2000 prices). Receipts subsequently declined with the fall in oil prices to a low of £1.0 billion in 1991/92 (equivalent to £1.3 billion in 1999/2000 prices) and are estimated to have totalled some £2.6 billion in 1999/2000. Since 1964/65, the Government has received a total of £90.9 billion in money of the day or £159.3 billion in 1999/2000 prices. Exchequer receipts since 1964/65 are given in Appendix 8. Receipts since 1976/77 are illustrated, together with oil prices and total oil and gas production, in Chart 2.10; receipts and oil prices are both shown in constant 1999/2000 prices.
Chart 2.10 - North Sea Tax Revenues and Oil Prices (in constant 1999/2000 prices) and Oil Equivalent Production

2.81 The offshore oil and gas industry has been responsible for the creation of not only direct employment both onshore and offshore, but also indirect employment and support to many other UK jobs.
2.82 The Office for National Statistics (ONS) give figures for employment classified to the oil and gas extraction sector, which includes not only those engaged in extraction offshore and onshore but also certain classes of contractors peculiar to the industry. Many oil related jobs such as construction workers are classified to other industries and are not included in ONS figures. ONS show employment at some 27,000 in 1978, peaking near 37,000 in 1990 and 1991, before falling sharply to around 25,500 in 1994 and 1995. Employment then recovered to near 29,000 between 1996 and 1999, but fell back to some 27,200 in 1999. These figures are illustrated in Chart 2.11.
Chart 2.11 - Employment in the oil and gas sector, and employment offshore, 1978 to 1999

2.83 Figures for offshore employment have been collected since 1967. The first annual surveys only collected numbers employed offshore on rigs and platforms and showed employment at just over 1,000 workers in 1967, rising steadily through the 1970s to 12,500 in 1978, before falling back in 1979. From 1980 onwards the survey included workers on pipe-laying vessels, crane barges, supply and standby vessels. The new survey showed offshore employment at 22,000 workers in 1980, rising to 31,300 in 1984, before slumping to near 22,000 in 1986. Offshore employment rose again to peak at 36,500 in 1990, after which there was a general downward trend with attempts to reduce costs. However, the 1993 and 1995 figures were both unexpectedly high due to the number of large fields under development on the day of the survey. These offshore employment figures are also shown in Chart 2.11.
2.84 These offshore surveys are co-ordinated by the Inland Revenue, with the support of industry provided through UKOOA (UK Offshore Operators Association), as the main purpose was to assist with tax compliance in the offshore oil and gas industry. Aggregated results are distributed to government and industry bodies and are used, for example, by the Health and Safety Executive and UKOOA to calculate accident and safety statistics. Changes were introduced in the September 1996 survey following an Inland Revenue initiative, which also assisted the industry aim to improve the accuracy of accident statistics. From 1999 onwards the survey is conducted twice a year, in February and August. The estimate for August 1999 was some 19,000. Table 2.10 shows offshore employment by type of work.
Table 2.10 - Offshore employment by type: 1999
| 1999 % |
|
| Production | 7.7 |
| Drilling/Work overs | 15.7 |
| Maintenance | 32.6 |
| Diving | 1.0 |
| Construction | 5.0 |
| Deck Operations | 8.1 |
| Management, Admin. & Catering | 15.2 |
| Transport Operations | 11.9 |
| Other/unidentified | 2.8 |
| 100.0 |
2.85 Aberdeen City and Aberdeenshire Councils have produced regular reports in which they give estimates for oil related employment in NE Scotland, both offshore and onshore. They estimate that this oil related employment had fallen steadily from 54,000 in 1991 to 40,000 in 1999 (of which 27,000 and 18,500 respectively were offshore). A significant point illustrating the rapid changes in the oil industry is that whereas they had estimated in 1997 that this employment would decline to 38,000 in 2006, they now estimate a decline to 34,000.
2.86 The National Training Organisation Group led by Offshore Petroleum Industry Training Organisation (OPITO) has completed a Labour Market study, and in March 2000 published a ‘Foresight’ report on future skills required in the industry. This was done on behalf of the Oil & Gas Industry Task Force, with the report being sponsored by DTI, Scottish Enterprise and the Department for Education and Employment. The aim is to improve the planning of training and education needs, identify new ways of working, and to improve performance.
2.87 UKOOA have commissioned studies to assess the number of UK jobs dependent directly or indirectly on the UKCS. The studies, which are based on analysis of input-output data, estimate that the UKCS directly and indirectly supported a total of some 250,000 jobs in 1995, and 210,000 in 1997. The estimate for 1997 includes some 34,600 jobs which are directly associated with offshore activities, and just over 175,000 additional jobs with suppliers and prime contractors and with their sub-contractors and others further down the supply chain. The studies estimate that a further 149,000 jobs depend on the spending of employment income by those in the 210,000 directly and indirectly supported jobs to give nearly 360,000 jobs affected by UKCS activity. A summary is shown in Table 2.11.
Table 2.11 - UKOOA’s estimates of employment affected by UKCS activity
| 1995 | 1996 | 1997 | |
| Direct jobs in the industry | 30,900 | 36,700 | 34,600 |
| Indirect job (supply chain) | 219,000 | 180,800 | 175,300 |
| Total direct and indirect | 249,900 | 217,500 | 209,900 |
| Induced jobs | 132,000 | 149,300 | 151,000 |
| Total including induced jobs | 381,900 | 368,500 | 359,200 |
UK/FAROES DELIMITATION AGREEMENT
2.88 A maritime boundary agreement between the United Kingdom and the Faroe Islands was signed in the Faroese capital, Tórshavn, on 18 May 1999. The agreement establishes the continental shelf boundary between the Faroe Islands and Scotland. A Designation Order (SI 1999 No 2031) made under the Continental Shelf Act 1964 came into force on 12 August 1999 giving the United Kingdom rights with respect to the sea bed and subsoil and their natural resources in the area up to the boundary. This enables the UK to offer petroleum licences for the new area, parts of which are recognised as having strong hydrocarbon potential.
Title
| Table of Contents
Chapter 1 | Chapter 2 | Chapter 3 | Chapter 4 | Chapter
5
Appendix 1 | Appendix 2 | Appendix 3 | Appendix 4 | Appendix
5 | Appendix 6 | Appendix 7 | Appendix 8 | Appendix 9
Appendix 10 | Appendix 11 | Appendix 12 |
Appendix 13 | Appendix 14 | Appendix 15 |
Appendix 16
Index Map | Plate 1 |
Plate 2W | Plate 2E | Plate 3W | Plate 3E | Plate
4W | Plate 4E | Plate 5W | Plate 5E | Plate 6
Plate 7 | Plate
8W | Plate 8E | Plate 9W | Plate 9E | Plate 10W | Plate
10E | Plate 11 | Plate 12 | Legend
Legal Notice